Step-by-Step Guide to Agile ITP Planning
-
Identify Your Boundaries
Determine the logical “sprint breaks” in your project, often tied to major milestones or distinct scopes of work.
For instance:
- Sprint 1: Earthwork, foundation and basement levels
- Sprint 2: Structural frame and envelope
- Sprint 3: MEP rough-ins and interior finishing
- Sprint 4: Commissioning, finishing touches and final inspections
These boundaries may shift as the project evolves, but having an initial outline helps each segment get its own ITP section.
-
Create a Framework with Placeholders
Even if final building configurations or code requirements for later sprintss aren’t yet confirmed, you can still reserve placeholders.
For example:
- Placeholder for Future Code Updates: “If local codes evolve by Sprint 3, re-check framing or insulation ITP items.”
- Potential Additional Structures: “If the client adds a mechanical annex, incorporate new system checks into the future ITP version.”
This approach keeps you from re-inventing your plan or scrambling to integrate new tasks when changes arise.
-
Detail the Immediate Sprint Thoroughly
For the sprint you’re about to begin, or the one currently in progress, create a comprehensive ITP section that includes:
- Inspection Points: Define the tasks needing verification (e.g., steel reinforcement, pre-pour checks).
- Acceptance Criteria: Reference relevant codes, design specs, or manufacturer guidelines.
- Hold/Witness Points: Identify especially critical tasks requiring official sign-off or an observer.
- Responsible Parties: Clarify which in-house or external entities oversee each inspection step.
-
Align Sprint Schedules with Inspection Needs
Tie each inspection item directly to the sprint project schedule. If foundation work starts on Monday, for instance, ensure the ITP calls for rebar checks by Sunday. Linking scheduling software with inspection tasks reduces the chance of overlooked work items, key in a large, multi-phase project where missed tasks can trigger widespread delays.
-
Communicate Sprint Updates in Real Time
For large-scale builds, mid-sprint design changes or newly introduced scopes can immediately affect the ITP. Ensure your system is set up so:
- Digital Tools: Everyone receives alerts if a new hold point or test is added for the current sprint.
- Regular Co-ordination: Weekly (or even daily) QA/QC meetings to confirm any changes and revise the relevant ITP items.
Managing Handoffs Between Sprints
When one sprint wraps up and the next is ready to begin, valuable quality data can get lost unless you plan carefully. Avoid this by:
- Finalizing and Storing Sprint Documentation: Collect all inspection logs, deficiency records, and sign-offs in a centralized repository.
- Carrying Over Lessons Learned: Use recurring deficiency data or problem areas from the completed sprint to strengthen your next-sprint ITP. If anchor-bolt misalignments were common, add extra hold points or training sessions for future structures.
- Kicking Off Next Sprint Meetings: Summarize the quality status from the recently completed sprint, address any open issues, and present updated ITP details so each new sprint starts on solid ground.
Pitfalls and How to Avoid Them
-
Overcomplicating Early Sprints
Some teams try to include every potential future detail in the first ITP version. This often sows confusion. Stick to what you can confirm and use placeholders for the rest. -
Insufficient Placeholder Clarity
Spell out exactly what ‘placeholder’ means and when it must be replaced with final data (e.g. “Add mechanical commissioning tests once final equipment selection is made”). -
Underestimating Sprint Transition Overlaps
Sprint 1 may still be finishing as Sprint 2 starts. Ensure the ITP accounts for overlaps, particularly if certain tasks extend into the next segment. -
Weak Communication
The bigger the project, the more critical it is to broadcast ITP updates widely. Employ digital QA/QC tools that push notifications to all relevant parties, from owners to subcontractors.
Example: Two-Tower Development
Consider a twin-tower residential project, built in two main phases. Obviously, there will be multiple sprints within each main phase. Main Phase 1 addresses Tower A’s structure and partial finishing, while Main Phase 2 includes Tower B from foundation to final fit-out. Early on, the client hasn’t decided whether to use a specialized solar facade for Tower B.
- Main Phase 1 ITP: Covers concrete, rebar, standard cladding, and MEP rough-ins. Hold points and acceptance criteria are fully set.
- Tower B Placeholder: “If solar facade is approved, incorporate specialized glazing checks, updated load calculations, and new electrical routing tests.”
- Mid-Phase Update: After six months, the facade design is finalized, so you revise the ITP for Tower B with fresh acceptance criteria and hold points. Alerts ensure the facade subcontractor and inspectors stay informed.
Conclusion
Agile ITP planning acknowledges a truth of large-scale construction: not all details are best hammered out at the beginning. By focusing on what’s needed now and keeping placeholders for the future, you maintain agility without sacrificing detailed inspections.
Combine this approach with pro-active communication, real-time digital updates, and a feedback loop that carries lessons forward and your multi-sprint development will uphold quality at every turn, no matter how massive or unpredictable the project scope becomes.
Download Inspection and Test Plans: The Definitive Guide to Proactive Digital QAQC for more insights on multi-sprint inspections and adapting to changing scopes.
Find out how to:
- Create and Implement Project-Specific ITPs
- Leverage Digital Tools for Real-Time QAQC
- Improve Quality, Reducing Rework, and Stay Audit-Ready
- Ensure Regulatory Compliance
Or look into a digital QA/QC platform such as FTQ360, that automates version control, real-time notifications, and deficiency tracking. Ensure you don’t miss critical inspections just because the project (inevitably) evolves.